Note: IPP means independent power producerPower station | Operator | Location | District | Province | Sector | Region | Capacity per unit (MW) |
Installed capacity (MW) |
Notes | Coordinates | Refs |
---|---|---|---|---|---|---|---|---|---|---|---|
Bangka Belitung 3 coal-fired | PT. BMP (IPP) | Air Anyir | Bangka | Bangka Belitung | Government | Sumatera | 2 x 30 | 60 | |||
Bukit Asam coal-fired | PT. PLN | Tanjung Enim | Muara Enim | South Sumatra | Government | Sumatra | 4 x 65 | 260 | Boiler from Stein, Turbines from Rateau and generators from GEC Alstom | [1] | |
Cilacap | PT. Sumber Segara Primadaya (IPP) | Karangkandri | Cilacap | Central Java | Government | Java-Bali | 2 x 300 | 600 | Boiler supplied by Dongfang Electric Corp. Ltd, Turbines and Generators supplied by Dongfang Electric Corp. Ltd | 07°40′31.20″S 109°05′47.40″E | |
Cilacap Adipala coal-fired | PT. Indonesia Power | Adipala | Cilacap | Central Java | Government | Java-Bali | 1 x 660 | 660 | Boiler supplied by Shanghai Electric Corp. Ltd, Turbines and Generators supplied by Shanghai Electric Corp. Ltd | [4] | |
Cirebon coal-fired | PT. Cirebon Electric Power (IPP) | Kanci Kulon | Cirebon | West Java | Private | Java-Bali | 1 x 660 | 660 | Boiler, Turbines and Generators supplied by Doosan Heavy Industries and Construction Co., Ltd. | 6.7704°S 108.6151°E | [4] |
Indramayu coal-fired | PT. PLN | Sumur Adem | Indramayu | West Java | Government | Java-Bali | 3 x 330 | 990 | Boiler supplied by Babcock & Wilcox Beijing Co., Turbines and Generators supplied by Beijing Beizhong | [4] | |
Labuan coal-fired | PT. Indonesia Power | Labuan | Pandeglang | Banten | Government | Java-Bali | 2 x 300 | 600 | Boiler supplied by Dongfang Electric Corp. Ltd, Turbines and Generators supplied by Dongfang Electric Corp. Ltd | ||
Labuhan Angin coal-fired | PT. PLN | Labuhan Angin | Central Tapanuli | North Sumatra | Government | Sumatra | 2 x 115 | 230 | Boiler supplied by China National Electric Equipment Corporation Corp. Ltd. (CNEEC), Turbines and Generators supplied by China National Electric Equipment Corporation Corp. Ltd. (CNEEC) | [5] | |
Lontar coal-fired | PT. Indonesia Power | Lontar, Teluk Naga | Tangerang | Banten | Government | Java-Bali | 3 x 315 | 945 | Boiler supplied by Dongfang Electric Corp. Ltd, Turbines and Generators supplied by Dongfang Electric Corp. Ltd | ||
Ombilin coal-fired | PT. PLN | Ombilin | Sawahlunto | West Sumatra | Government | Sumatra | 2 x 100 | 200 | Boiler from Stein, Turbines and generators from GEC Alstom | [1] | |
Pacitan coal-fired | PT. PLN | Sukorejo | Pacitan | East Java | Government | Java-Bali | 2 x 315 | 630 | Boiler supplied by Dongfang Electric Corp. Ltd, Turbines and Generators supplied by Dongfang Electric Corp. Ltd | [4] | |
Paiton | PT. Paiton Energy (IPP) | Paiton | Probolinggo | East Java | Private | Java-Bali | 2 x 670, 2 x 610, 1 x 850 | 2,300 | Boiler supplied by ABB, Turbines and Generators supplied by GE | [4] | |
Paiton (PLN) coal-fired | PT. PLN | Paiton | Probolinggo | East Java | Government | Java-Bali | 2 x 400 | 800 | Boiler from ABB Combustion Engineering, Turbines and generators from Toshiba | 7.7155°S 113.5849°E | [2] |
Pelabuhan Ratu coal-fired | PT. Indonesia Power | Pelabuhan Ratu | Sukabumi | West Java | Government | Java-Bali | 3 x 350 | 1050 | Boiler supplied by Shanghai Electric Corp. Ltd, Turbines and Generators supplied by Shanghai Electric Corp. Ltd | [6] | |
Rembang coal-fired | PT. PLN | Sluke | Rembang | Central Java | Government | Java-Bali | 2 x 315 | 630 | Boiler supplied by Dongfang Electric Corp. Ltd, Turbines and Generators supplied by Dongfang Electric Corp. Ltd | 06°38′18.21″S 111°28′27.41″E | [4] |
Suralaya Baru coal-fired | PT. Indonesia Power | Suralaya | Cilegon | Banten | Government | Java-Bali | 1 x 625 | 625 | Boiler from Shanghai Co. Ltd, Turbines and generators from Shanghai Co. Ltd | 5.892°N 106.03°E | [3][4] |
Suralaya coal-fired | PT. Indonesia Power | Suralaya | Cilegon | Banten | Government | Java-Bali | 4 x 400 3 x 600 |
3,400 | Boiler from Babcock & Wilcox Canada, Turbines from MHI Japan; generators from Mitsubishi Electric Co. | ||
Tanjung Jati-B I coal-fired | PT. Central Java Power (IPP) | Bangsri | Jepara | East Java | Private | Java-Bali | 2 x 662 | 1,320 | Boiler supplied by Babcock & Wilcox, Turbines and Generators supplied by Toshiba | [4] | |
Tanjung Jati-B II coal-fired | PT. Central Java Power (IPP) | Bangsri | Jepara | East Java | Private | Java-Bali | 2 x 662 | 1,320 | Boiler supplied by Mitsubishi Heavy Industry, Turbines and Generators supplied by Toshiba | [4] | |
Tarahan coal-fired | PT. PLN | Tarahan | South Lampung | Lampung | Government | Sumatra | 2 x 100 | 200 | Boiler supplied by Jinan Co. Ltd, Turbines and Generators supplied by Wuhan Co. Ltd | ||
Total | 50 | 18,630 |
Proposed or under construction
Power station | Operator | Location | District | Province | Sector | Region | Capacity per Unit (MW) |
Installed Capacity (MW) |
Remarks and Plant Coordinates |
---|---|---|---|---|---|---|---|---|---|
Central Java coal-fired (by the end of 2016) | PT. Bhimasena Power Indonesia | Ujungnegoro | Batang | Central Java | Private | Java-Bali | 2 x 1000 | 2,000 | [7] |
Tanjung Awar-Awar coal-fired | PT. PLN | Kaliuntu | Tuban | East Java | Government | Java-Bali | 2 x 350 | 700 | Boiler supplied by Babcock & Wilcox Beijing Co. Turbines and generators supplied by Beijing Beizhong |
Madura coal-fired | PT. PLN | Pamekasan | East Java | Government | Java-Bali | 2 x 100 | 200 | ||
Bojonegara coal-fired | PT. PLN | Bojonegara | Cilegon | Banten | Government | Java-Bali | 3 x 740 | 2,220 | |
Tanjung Jati-A coal-fired | PT. Bakrie Power | Cirebon | Cirebon | West Java | Private | Java-Bali | 2 x 660 | 1,320 | |
Nusa Penida coal-fired | PT. PLN | Nusa Penida | Bali | Government | Java-Bali | 2 x 100 | 200 | ||
Anyer coal-fired | PT. PLN | Anyer | Banten | Government | Java-Bali | 1 x 330 | 330 | ||
Kuala Tanjung coal-fired | PT. Ranyza Energi | Kuala Tanjung | South Sumatra | Private | Sumatra | 2 x 112 | 224 | ||
Banjarsari coal-fired | PT. Bukit Pembangkit Innovative | Banjarsari | Lahat | South Sumatra | Private | Sumatra | 2 x 100 | 200 | |
Banyuasin coal-fired | PT. Banyuasin Power Energy | Banyuasin | Banyuasin | South Sumatra | Private | Sumatra | 2 x 100 | 200 | |
Baturaja coal-fired | PT. Priamanaya Power Energi | Baturaja | Ogan Komering Ulu | South Sumatra | Private | Sumatra | 2 x 100 | 200 | |
Simpang Belimbing coal-fired | PT. GH EMMI | Gunung Raja | Muara Enim | South Sumatra | Private | Sumatra | 2 x 150 | 300 | |
Arahan coal-fired | PT. PLN | Arahan | Muara Enim | South Sumatra | Government | Sumatra | 4 x 600 | 2,400 | |
Central Bangko coal-fired | PT. BA & CHD (China)[11] | Bangko Tengah | Muara Enim | South Sumatra | Private | Sumatra | 4 x 620 | 2,480 | |
Tanjung coal-fired | PT. PLN | Tanjung | Tabalong | South Kalimantan | Government | Kalimantan | 2 x 55 | 110 | |
Total | 34 | 13,084 |